In association with
Logo Logo Logo

Upper Tamakoshi in final state, tunnel ready by April 21

Photo: Wikipedia

KATHMANDU: The ongoing Upper Tamakoshi Hydropower Project (456 MW) has reached final stage of construction. Major works as intake, tunnel, transmission line, and substation have been completed.
There are now minor civil and mechanical works going on under the project. Although one of the national pride projects was expected to be completed before coming New Year (2078BS), it was delayed because of Covid-19 and some technical glitches. Lot-2 Hydro-mechanical contractor company has committed that the works as wielding and painting would be completed by April 21. Similarly, the installation of penstock pipe has been over.
Embankment/intake, main tunnel, power house, tail race tunnel as part of the major construction have also been completed. Executive Director at Nepal Electricity Authority and Chairperson of Upper Tamakoshi Hydropower Ltd, Hitendra Dev Shakya, conducted an inspection visit and held discussion with project officials, consultants and contractors on the schedule of releasing water to the tunnel with speedy completion of the remaining works. Shakya shared that power production would begin from mid-May.

Comment here !
Related News

KATHMANDU:- Nepal’s economy is anticipated to grow by 4.1% (at market prices) in fiscal year (FY) 2022, up from an

KATHMANDU;- The Asian Development Bank (ADB) has projected 4.2 percent growth rate in Nepali economy next year, 2022. Updating its

KATHMANDU;-Newly appointed Minister for Foreign Affairs, Dr Narayan Khadka, has said that a balanced relation would be maintained with all

KATHMANDU:- The Asian Development Bank (ADB) has approved a 60 million USD loan as additional support for the ongoing Electricity