Super Dordi ‘B’ Project completes tunneling of 5.1-km passage, production likely in 8 months


LAMJUNG:- Drilling of a major tunnel under the Super Dordi ‘B’ Hydropower Project in Lamjung has been carried out.
The under-construction 54-megawatt project based in Dhodheni of Dordi rural municipality-6 of Lamjung, the hilly district in Gandaki Province, reports the completion of drilling of the 5.1 kilometers underground passage.
Despite hurdles caused by the 2015 earthquake, and subsequent economic blockade in the southern border and COVID-19 crisis, the project succeeded in making a breakthrough. According to the People’s Hydropower Company, the project developer, works to dig the underground passage have been completed and it has been taken as the major achievement.
Company managing director Keshab Bahadur Rayamajhi said they target to generate electricity within the next seven to eight months as the project so far reports the 85 percent progress.
Fixing of equipment is going on for the project power house. The flood from the river in last July had caused damage to the project dam side and it is being restored.
Nine banks including the Sanima (major investor) have invested in the project. The total investment of the project is Rs 8.80 billion. People of project-affected districts have invested Rs 270 million for the project.
As per the Power Purchase Agreement, the project will supply power at eight rupees four paisa in the dry season and at four rupees eighty paisa during the summer monsoon. The total gross head of the run-of-the-river project is 640 meters and it has the capacity of producing around 315,000,000 units of electricity annually.

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

Comment here !
Related News

KATHMANDU:- The Millennium Challenge Corporation (MCC) Compact has been published in the Nepal Gazette, the government’s official bulletin. With this,

KATHMANDU:- Although agriculture has been a major sector of the country’s economy as the main source of livelihood, employment and

KATHMANDU:- The third BIMSTEC energy ministerial meeting of the Bay of Bengal Initiative for Multi-Sectoral Technical and Economic Cooperation (BIMSTEC)

KATHMANDU:- The Ministry of Finance (MoF) has issued a directive to different ministries, agencies and public agencies to reduce fuel


Headlines
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point