Successful test of power production by Upper Syange project


LAMJUNG:- The Upper Syange Hydropower Project here has successfully tested 2.4 MW of electricity generation. The power generation test of the project located in Marsyangdi Village Municipality Ward No. 4 Mipra was successful.
The construction of the project was completed in September and testing has been started since December 8. “We have communicated to the Nepal Electricity Authority to connect the generated power to the national grid. Testing of hydromechanical and electromechanical equipment of civil structures and connected equipment has been successful,” said Som Tamang, technician at the project.
The construction of the project was started in 2074 BS. Technician Tamang informed that the project will be connected to Khudi substation at a distance of 12 km through 33 KV transmission line. The project will generate 14.616 gigawatt hours of electricity annually.
Similarly, the project can generate 2.868 gigawatt hours of electricity in winter and 11.748 gigawatt hours in rainy season. The construction of the project has been completed at a cost of Rs 500 million, according to Upper Syange Hydropower Limited.

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

Comment here !
Related News

PARIS, (AFP):- More than 80 fact-checking organisations Wednesday urged online video platform YouTube to better combat disinformation, offering to help

SAN FRANCISCO (AP):- Twitter on Sunday banned the personal account of Rep. Marjorie Taylor Greene for multiple violations of its

KATHMANDU:- The Computer Association of Nepal (CAN) Federation is going to organize the 27th edition of CAN Info-Tech Fair from

By Ramesh Lamsal, KATHMANDU:- The demand for electricity has increased significantly in the domestic market, thanks to effective policy, practical