Optical fiber backbone project: fiber laid on1,600 kilometers


By Samundra Ghimire, KATHMANDU:- Optical fiber has been installed along 1,600 kilometers length so far under the Optical Fiber Backbone Network Expansion Project across the country.
Nepal Telecom Authority (NTA) had initiated the project with a goal of expanding optical fiber network within two years, but only 46.16 per cent of work has been completed till July 15.
The Nepal Telecom, which had got responsibility of laying optical fiber in province 1, 2 and Bagmati Province under the first phase, has completed installing the optical fiber in these areas.
As per the agreement, the NT has to install optical fiber along 2,083 kilometers in three provinces. Of them, it has laid fiber along 1,006 kilometers in five years. The NTA had given the responsibility to install fiber at 6,235 kilometers of mid-hill highway to three separate companies dividing the project in three sections.
Out of three sections, fiber laying work has been started, the work has not started yet. The NTA had signed agreement with Nepal Telecom on September 28, 2012 in order to lay fiber from eastern Nepal to Gorkha within two years under the first section.
NTA Spokesperson Santosh Poudel said that the Nepal Telecom had started laying optical fiber from mid-May 2019.
He shared the Nepal Telecom has given responsibility to five companies to lay optical fiber and purchase goods for the same in three provinces under the first section.
Works on two sections stalled
Works have not begun in two sections of the information superhighway expansion project divided into three sections. The installation of optical fibre has not begun in the 2,160 kilometres in 21 districts of Gandaki and Lumbini provinces under Section-2.
Although NTA has given the responsibility to the United Telecom (UTL) for the expansion, the expansion works are halted as a case has been filed against it in the Supreme Court. The NTA had signed a contract worth Rs 2.01 billion with UTL on May 8, 2017.
NTA annulled the contract with UTL on May 9, 2019 citing the latter failed to start works on the project within the specified period. After this, UTL moved the Supreme Court.
Under the project, optical fibre of 98 core would be installed along the Mid-Hill highway, of 48 core would be laid down along the roads linking the district headquarters and the Mid-Hill highway with the East-West highway while optical fibre of 24 core would be installed alongside the roads connecting the municipalities.
NTA is refusing to continue the project with Smart Telecom as the firm has not been able to make tangible progress in the project works despite repeated directions from the authority.
Though NTA is in the mood to award the optical fibre laying project across the Karnali Province and Sudurpaschim province to a new company, it is still undecided on when to open the new tender.
Though Smart Telecom was supposed to lay the optical fibre cables along almost 2,500 kilometres in different parts of the two aforementioned provinces, it has so far laid only 20 kilometres of optical fibre, as per NTA. In the case of UTL, which was supposed to lay optical fibre across almost 2,000 kilometres in Gandaki Province and Lumbini Province, it has not even started the project work. As UTL failed to comply with the project agreement, NTA had scrapped the project contract with UTL.
However, NTA is yet to appoint a new developer of the project in these two provinces. Similarly, Nepal Telecom, that is supposed to lay optical fibre across Provinces 1, 2 and Bagmati Province has just started the project citing different procedural hurdles. As none of these firms have been able to give proper shape to the optical fibre project, the project worth billions of rupees faces uncertainty at the moment. NTA is funding these projects through the Rural Telecommunications Development Fund.
Meanwhile, Min Prasad Aryal, spokesperson for NTA, said that the authority will soon take necessary decisions regarding the project in consultation with the Ministry of Communications and Information Technology.
The project envisages connecting 32 districts in Provinces 1, 2 and Bagmati with high-speed optical fibre to allow fast data transfers and voice and video calls, according to the state-owned telecom giant. RSS

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

Comment here !
Related News

MITZPE RAMON, ISRAEL, (AFP):- Inside a huge crater in Israel’s sun-baked Negev desert, a team wearing space suits ventures forth

SAN FRANCISCO, (AFP):- Facebook on Friday said users around the world again had problems accessing its services for hours due

KATHMANDU:- Minister for Communications and Information Technology Gyanendra Bahadur Karki assumed the office today. Taking charge of the ministry, newly-appointed

SIMKOT:- Nepal Telecom services have witnessed technical problems at Adanchuli Rural Municipality, located in the southern belt of Humla district.


Headlines
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point