Ilam will not have electricity for a month


ILLAM: Electricity will be disrupted in Ilam district for a month after a transformer brought from Hetauda exploded.   The 1.5 MVA (Mega Volt Ampere) transformer brought two days ago from Hetauda  by Nepal electricity authority NEA burst while installing, said NEA Ilam Branch Chief Rajib Kumar Sharma.

Electricity was disrupted after the transformer here exploded on Sunday due to lightning affecting 20 VDCs including Ilam, the district headquarters and news papers and FMs here have been closed.

The bridge at Maikhola will not sustain the 29 tons of load of crane and transformer planned to be brought from Damak, Jhapa and alternate method  should be arranged,  said Engineer of the Eastern Road Division Office Ilam,  Arun Karna. RSS

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

Comment here !
Related News

KATHMANDU:- The government has decided to form a high-level salary and facilities commission for reviewing the minimum salary, allowances, remuneration

KATHMANDU:- The Supreme Court (SC) on Tuesday gave its verdict on the dispute over civil servants’ adjustment. With the verdict,

KATHMANDU:- Nepali Congress leader and thinker Pradip Giri, who had been undergoing treatment for cancer at Mediciti Hospital, Lalitpur, passed

KATHMANDU:- A total of 84 political parties, including old and new ones have submitted their applications for party registration for


Headlines
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point