Chameliya hydel project construction begins after four months


Gokuleswor (Darchula): Construction of Chameliya Hydropower Project has started Tuesday after four months of disruption.
China Gerjuwa Group of Power Company (CGGC) – which was awarded a contract for civil construction part of the project – had halted construction works for an indefinite time citing Nepal Electricity Authority (NEA)’s non-compliance to make timely payment in line with the contract.
Project Chief Rajendra Manandhar said the construction works begun since Tuesday after NEA cleared payment to CGGC. With grinding halt of civil construction works, the electro mechanical works led by the Korean Company were also affected.
According to the Chameliya Hydropower Project sources, the Chinese Company has completed 95 per cent of the total civil construction works including digging out of around 4.5-km-long tunnel.
The timeline of the project that started construction since 2007 with the investment of around Rs 13 billion has been extended to March 2015 as the target to accomplish the project by 2011 was failed due to several reasons, said Project Chief Manandhar.
The under construction 30-MW Chameliya Hydropower Project is so far the biggest hydel project in the far-Western region. RSS

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

For Indian tourists travelling by land:- 72 hours (-ve) C-19 report, CCMC form and Antigen Test at entry point

Comment here !
Related News

KATHMANDU:- The Millennium Challenge Corporation (MCC) Compact has been published in the Nepal Gazette, the government’s official bulletin. With this,

KATHMANDU:- Although agriculture has been a major sector of the country’s economy as the main source of livelihood, employment and

KATHMANDU:- The third BIMSTEC energy ministerial meeting of the Bay of Bengal Initiative for Multi-Sectoral Technical and Economic Cooperation (BIMSTEC)

KATHMANDU:- The Ministry of Finance (MoF) has issued a directive to different ministries, agencies and public agencies to reduce fuel


Headlines
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point
Information for Indian tourists travelling by land:- 72 hours (-) C-19 report, CCMC form and Antigen Test at entry point